Making a Schedule
I wanted to make a loose schedule of certain goals that I want to meet as the weeks go on for this project. I'll order the groups by the weeks from the beginning to the end.
Week One (2/13-2/17): Week one was an important stage of basic introductory research and some potential brainstorming of ideas. Week one was successful in those aspects, I completed my blog posts and my research on my genre was finished. Although an idea was not created just thinking about potential ideas was helpful.
Week Two (2/17-2/23): Week two should consist of some planing as I am doing now, just so I have a basic outline to follow while doing the project. Since my pacing should always be on my mind. More brainstorming should be done to hopefully by the end of this week have some idea of what i'll create as my film opening. More research will be done to get more ideas, consuming more horror content and film openings should be helpful.
Week Three (2/24-3/1): By week three if an idea is not found it will be finalized and the project will head into pre-production. This week will be a week of location scouting, planning out how to film the opening. Doing research on lighting techniques and how to color-grade video so I can get the look that I want. During this week I plan on making a light script outline, and create some visual storyboards with pictures.
Week Four (3/2-3/8): By this week all I should be doing is filming the project. I don't expect to do much other than film. Some research may occur if I need to learn how to do something while on set.
Week Five (3/9-3/15): Week five should be any extra filming if any is even needed. The editing process will start here, during this stage I will create a first draft of the completed product without sound effects or music. I will choose the music that I want for the project and do some light sound effects and some more refining of the flow of the project. If I need to do some research on how to edit something that would be done during this week. Some posts will be done in advanced to prepare for the upcoming spring break.
Week Six (3/16-3/22): This week I will be on target to finish the editing, almost completely, with sound effects and music being final. Any other edits will be done to improve flow and coherence of the film. Although I am not sure if the project will be finished editing. The majority of this week will be doing blog posts in advance for the upcoming spring break. If on target i'll do no work during the break and the next two weeks after the break will go smoothly and be on target.
Week Seven (3/23-3/29) SPRING BREAK: To be honest I do not plan on doing any work this week, as it is the break I will plan my postings ahead during week six. Editing of the project should be done during week six. My goal for this week is to get any work done that would have been done for this week beforehand so I can enjoy my break.
Week Eight (3/30-4/5): By week eight I want to be completely done with editing the project, but if I still am editing and refining the project i'll consider that to be on schedule. If the project was almost done and edited before this week. I want this week to be mostly focused on on creative critical reflection and any blog posts relating to what my journey was like creating the film opening. I want this week to be a week of refining and reflection.